Electrical Costs from National Grid Push Up Costs of Rear Main Street Project – Gardner Redevelopment Authority Meets
Listen to the entire meeting (except for the Executive Session) on any device, CLICK PLAY.
During the Gardner Redevelopment Authority meeting on March 10, 2026, officials discussed critical budget overruns for the Rear Main Street project, largely caused by a 350% increase in electrical costs from National Grid. The director detailed how a previous decision (by the previous director) to use low estimates to secure grants has now led to a funding gap that requires reallocating surplus money from other projects. Regarding the South Main project, the board weighed the pros and cons of leasing land versus using eminent domain to avoid further delays. Additionally, the group reviewed the stalled sale of 155 Mill Street to Waterstone, expressing frustration over the developer’s changing demands and potential liability issues. The meeting concluded with updates on industrial park interest and a plan to seek legal and ethics advice concerning member conflicts and property sales.