Awaited Transformer to “Jumpstart” stalled 25 Main Street Project
The wait for a transformer had put certain aspects of the 25 Main Street project on hold. A relieved Jon Bombaci posted about the recent development in the long process “The transformer is finally here! Our 25 Main Street in Gardner project has been sitting in limbo—intentionally delayed because we didn’t have enough power to turn it on. After 18 months of radio silence and vague timelines, I got a call two weeks ago that the transformer was going in on 4/30. Honestly, I didn’t believe it… but here we are. Now it’s time to go full send and bring this project back to life. “