Construction Affecting the Entrance to Gardner MA City Hall
Gardner Mayor Michael Nicholson released the following statement:
City Hall Entrance Construction Notice
Beginning Monday, March 23, the City will begin the construction at City Hall which will affect the accessibility ramp and front entrance.
Phase 1: Accessibility Ramp Work
Construction on the accessibility ramp (located under the connector overpass between City Hall’s main building and Annex) will begin on Monday, March 23, with an anticipated completion between Wednesday, March 25 and Thursday, March 26.
Access to the ADA entrance will remain open and operational during this time, available via the Knowlton Street parking lot. — The front entrance of City Hall will remain open during this phase.
Phase 2: Front Entrance Work
Following completion of the accessibility ramp, construction will begin on the front entrance of City Hall, with an estimated start date of Friday, March 27. — The front entrance will be closed during this phase. Public access will be available through: The ADA entrance — The “Employee Only” entrances within the Knowlton Street and Connors Street parking lots will be unlocked for public use.
Construction on the front entrance is expected to take approximately one (1) month. A more specific timeline will be provided once the accessibility ramp work is complete.
Project Timeline Overview: Accessibility Ramp: Start Date: Monday, March 23 – Estimated Completion: Thursday, March 26 — Front Entrance: Estimated Start Date: Friday, March 27 Estimated Duration: Approximately one (1) month